Next Generation Regional Communications System- User Migration.
Posted on Friday 03/02/2018
https://www.rcs800mhz.org/announcements
https://www.rcs800mhz.org/advisories
Completion of the equipment and antenna installation is planned for the June 2018 time frame.
operational and acceptance testing of the new network will start and run through the end of 2018.
Project staff will start migrating users from the current network to the NextGen network in early 2019. Planning for this transition process is underway and details will be released when they are available later this year.